POWER GENERATION

Two-phase commissioning at new energy-from-waste power station with compact footprint

Limited space at a new energy-from-waste (EfW) plant in northern Germany posed difficulties. The compact site meant Ecolutia had to find an alternative feedwater connection point and relocate equipment two months later.

CLIENT
Power station operator: new build energy-from-waste plant
LOCATION
Germany
SERVICE
Commissioning: Demin production and condensate polishing
DURATION
Phase 1: 7 months
Phase 2: 12 months
THE CHALLENGE

A compact construction site with limited open space

During construction of a new energy-from-waste (EfW) power station in Germany, Ecolutia was asked to provide a temporary demineralized water production and condensate recovery solution.

With a compact layout, the active construction site presented several difficulties at the beginning of the project. An earlier site visit identified a flat location for Ecolutia equipment to be placed, but as Ecolutia equipment began arriving the pre-agreed location was already in use for other construction activities. The limited site footprint meant the Ecolutia team had to act quickly to find a new level surface on an already crowded construction site.

The Ecolutia Field Service Engineers (FSEs) co-ordinated with the customer and other suppliers on site to find a suitable space that would not impede ongoing construction work. With some site adjustments a new space was deemed suitable, but the new equipment location meant connecting hoses to the original feedwater access point would hamper others working in the area. A workable solution was achieved with agreement from the customer for Ecolutia to use a nearby street hydrant on the site.

THE SOLUTION

Relocate, re-connect, and add a condensate polishing stage

After some months of working with the revised layout the customer asked for a change to start the next phase of the new plant commissioning. To accommodate arrival of condensate polishing units for treatment of boiler feedwater, Ecolutia relocated its HydroPURE units to a new position.

With the expansion, the existing units moved beneath the ACC fans and adding a Proteus Series unit loaded with GAC allowed filtration of the return condensate water. The second HydroPURE unit added the condensate polishing step, and a Proteus Solo skid provided back-up filtration, should it be needed. Relocating and installing new systems also required decoupling, relaying and reconnecting all hoses used for the entire project.

TREATMENT FLOW PATH
PHASE 1
HYDROPURE
Demineralization
PHASE 2
PROTEUS
GAC filtration
HYDROPURE
Condensate polishing
THE RESULTS

From site visits to 24/7 Ecolutia cover

During the initial phase, this project needed demineralized water intermittently, so it was managed by regular FSE site visits combined with Ecolutia’s remote monitoring solution. Ecolutia initially commissioned the HydroPURE unit and set up an automated production sequence when the break tank level dropped to a set level. This setup ensured demin water production was always available and the systems automatically filled the tank and shut down when the upper tank level was achieved.

Once the additional equipment was installed the commissioning phase increased in pace, so Ecolutia began to operate the site on a 24/7 basis. Three FSEs worked on 8-hour shift rotations to keep the demin water production operational, the storage tank level high, and the condensate polishing system running whenever it was needed.

As the new power station construction project was in proximity to residential areas, certain restrictions meant the steam blow and other commissioning activity were limited to certain times. The resulting frequent shutdown and startup events meant Ecolutia FSEs had to remain available on site to operate and maintain equipment so tank levels could be sustained at short notice.

After two months the customer finished the condensate polishing stage so reverted back to the phase 1 setup of having one HydroPURE unit on site, to provide demineralized water for the remaining part of the site commissioning.

<0.1 µS/cm
PRODUCT WATER CONDUCTIVITY
110–480 GPM
DEMIN PRODUCT WATER FLOW RANGE
24-hour
FSE COVER
ON SITE
MORE CASE STUDIES

Explore related projects

VIEW ALL
POWER GENERATION

Commissioning an air-cooled condenser on a zero-discharge site

ACC condensate polished back to demineralized quality on a zero-discharge site in France.

DATA CENTERS

Hardness out of the cooling loop at a hyperscale data center

HydroPURE softening held cooling make-up hardness below 1 ppm, with N+1 redundancy intact at a hyperscale data center.

PETROCHEMICAL

Oxygen removal from boiler feed water — with the deaerator offline

Oxygen removal at ambient temperature while a refinery’s deaerator was offline.