POWER GENERATION

24/7 seawater to demin for new coal power plant commissioning at a remote copper mine

A coal-fired station under construction in Chile’s Lake District needed 315,000 GPD of demineralized water for a steam blow — more than its own plant could make. Ecolutia produced it from an open seawater intake.

CLIENT
EPC – new build coal-fired power station
LOCATION
Chile
SERVICE
Commissioning: steam blow
DURATION
7 months, 24/7
THE CHALLENGE

Demin from seawater, in a remote region

The steam blow phase required more treated water than the onsite plant — sized only for the station’s daily needs — could produce. The customer needed an average of 315,000 gallons of demineralized water every day, continuously, to keep the steam blow progressing without interruption.

The project site is in a remote part of the country, and the only available feedwater source was an open seawater intake with a salinity of up to 51 mS/cm — demanding significant additional treatment before the RO membranes could even begin to treat it.

THE SOLUTION

Filtration, double-pass RO and regen-in-place polishing

Two Proteus systems provided two-pass multimedia and GAC pre-filtration to <0.5 NTU and <3 SDI at 660 GPM. A Triton SWRO (40% recovery, 99.4% rejection) and BWRO in series took conductivity from 51 mS/cm to just 5 µS/cm, and a third Proteus setup with duty/standby ion-exchange trains polished to the final demineralized water quality — regenerated in place to avoid shipping resin long distances to a regeneration service facility.

PLC automation across the fleet, networked over Ethernet for data exchange and automated shutdown
Remote monitoring enabling 24-hour production with fewer engineers needed on site
Drinking-water-compatible chemicals — backwash and brine returned directly to the sea
TREATMENT FLOW PATH
MMF
Multi-media filtration
GAC
Activated carbon
SWRO
Seawater RO
BWRO
Brackish water RO
IX
Ion exchange polish
THE RESULTS

Over 95% availability — with an unexpected extra step

Backwash intervals stretched to five days, keeping availability and water efficiency above 95% and the DI tanks permanently topped up, at under 9.5 kWh/kgal from seawater to demin. When the site’s own ion-exchange plant was not ready, Ecolutia’s engineers quickly reconfigured the fleet to polish evaporator water as well — and the steam blow completed quickly, entirely on Ecolutia water.

315,000 gal
PRODUCED PER DAY
0.06 µS/cm
PRODUCT CONDUCTIVITY
>95%
SYSTEM AVAILABILITY
<9.5 kWh/kgal
SEA-TO-DEMIN POWER USE
ON SITE
MORE CASE STUDIES

Explore related projects

VIEW ALL
POWER GENERATION

Commissioning an air-cooled condenser on a zero-discharge site

ACC condensate polished back to demineralized quality on a zero-discharge site in France.

OIL & GAS

Outsourced water plant for a Southeast Asian crude oil refinery

A 10-year outsourced RO permeate plant running at under 3.8 kWh/kgal.

FOOD & BEVERAGE

Generating a valuable water resource from milk evaporator condensate

Milk evaporator condensate recovery for reuse at a German dairy.

NEED SEAWATER TREATMENT?
Demin water from any source, fast.
REQUEST A CONSULTATION