24/7 seawater to demin for new coal power plant commissioning at a remote copper mine
A coal-fired station under construction in Chile’s Lake District needed 315,000 GPD of demineralized water for a steam blow — more than its own plant could make. Ecolutia produced it from an open seawater intake.
CLIENT
EPC – new build coal-fired power station
LOCATION
Chile
SERVICE
Commissioning: steam blow
DURATION
7 months, 24/7
THE CHALLENGE
Demin from seawater, in a remote region
The steam blow phase required more treated water than the onsite plant — sized only for the station’s daily needs — could produce. The customer needed an average of 315,000 gallons of demineralized water every day, continuously, to keep the steam blow progressing without interruption.
The project site is in a remote part of the country, and the only available feedwater source was an open seawater intake with a salinity of up to 51 mS/cm — demanding significant additional treatment before the RO membranes could even begin to treat it.
THE SOLUTION
Filtration, double-pass RO and regen-in-place polishing
Two Proteus systems provided two-pass multimedia and GAC pre-filtration to <0.5 NTU and <3 SDI at 660 GPM. A Triton SWRO (40% recovery, 99.4% rejection) and BWRO in series took conductivity from 51 mS/cm to just 5 µS/cm, and a third Proteus setup with duty/standby ion-exchange trains polished to the final demineralized water quality — regenerated in place to avoid shipping resin long distances to a regeneration service facility.
PLC automation across the fleet, networked over Ethernet for data exchange and automated shutdown
Remote monitoring enabling 24-hour production with fewer engineers needed on site
Drinking-water-compatible chemicals — backwash and brine returned directly to the sea
TREATMENT FLOW PATH
MMF
Multi-media filtration
GAC
Activated carbon
SWRO
Seawater RO
BWRO
Brackish water RO
IX
Ion exchange polish
THE RESULTS
Over 95% availability — with an unexpected extra step
Backwash intervals stretched to five days, keeping availability and water efficiency above 95% and the DI tanks permanently topped up, at under 9.5 kWh/kgal from seawater to demin. When the site’s own ion-exchange plant was not ready, Ecolutia’s engineers quickly reconfigured the fleet to polish evaporator water as well — and the steam blow completed quickly, entirely on Ecolutia water.
SENDING…Sorry — your message could not be sent. Please try again, or email info@ecolutia.com.We could not send your application just now. Please try again, or email it to info@ecolutia.com.Sorry, that was too quick for our spam check. Please press Send again.Please complete the human verification and try again.Please enter a valid email address.Please fill in the required fields.