High flow pure water production with zero downtime, within a fully operating oil refinery

A countrywide sulphuric acid shortage forced a refinery to stretch the time between ion-exchange regenerations. Three mobile RO units were integrated into the live plant at 180 m³/h, with no interruption to production.

CLIENT
Oil refinery
LOCATION
Germany
SERVICE
Temporary: RO permeate production
DURATION
12 months
THE CHALLENGE

An acid shortage, and no room to stop

A countrywide shortage of sulphuric acid was taking place during a higher oil refinery production period. This meant a large oil refinery in Germany could not regenerate its own ion-exchange (IX) resin as normal. A continuous delivery of high-purity water is critical for steam generation, cooling, and process applications at the refinery. Any disruption could force reductions in throughput or unplanned refinery shutdowns.

The refinery urgently sought to integrate temporary brackish water reverse osmosis (RO) systems into its existing water treatment process. With production at full capacity the installation had to be completed without any disruption to the refinery operations.

THE SOLUTION

Three mobile RO units integrated within a live operational refinery

Ecolutia smoothly integrated three Triton BWRO96 reverse osmosis systems into the onsite water treatment process. Operational within a few days in a parallel configuration, the high-quality RO permeate, at a flowrate of 180 m³/h, ensures refinery operations are not disrupted.

Integrating between the onsite filtration and ion-exchange systems allows the ROs to receive a filtered municipal feedwater with lower NTU and SDI levels. This supports high-quality RO permeate production, so the downstream ion-exchange system can run at full capacity with the advantage of regenerating the resin less frequently, thereby significantly reducing chemical and manpower needs.

Precise timings and communication between Ecolutia and refinery engineers were the key to avoid disruption to the water treatment process and other onsite operations. Scheduling backwashes of the upstream filtration feeding the Ecolutia ROs was essential to maintain sufficient pressure and flow within the units so downstream water production could continue.

TREATMENT FLOW PATH
FEED
Municipal water
MMF
Customer’s multi-media filtration
BWRO
Ecolutia’s 3 x brackish water reverse osmosis
IX
Customer’s ion-exchange demineraliser
THE RESULTS

Six months planned, twelve months delivered

The initial planned 6-month project was a success and helped improve demineralised water production, such that the customer signed a 6-month extension.

The RO permeate consistently produced water with >95% contaminant rejection at flows of 180 m³/h, 24 hours a day, 7 days a week. This ensured minimal disruption and downtime to the customer’s process, allowing them to focus on other on-site activities.

The remote monitoring system Ecolutia employs has enabled rapid response times when the customer has requested a change in flow conditions, as well as the ability to monitor the process whilst off-site to ensure a smooth operation.

180 m³/h
PERMEATE TO THE IX SYSTEM
>95%
CONTAMINANT REJECTION
3
TRITON BWRO96 UNITS
ON SITE
MORE CASE STUDIES

Explore related projects

VIEW ALL
PETROCHEMICAL

Oxygen removal from boiler feed water — with the deaerator offline

Oxygen removal at ambient temperature while a refinery’s deaerator was offline.

POWER GENERATION

Commissioning an air-cooled condenser on a zero-discharge site

ACC condensate polished back to demineralised quality on a zero-discharge site in France.

DATA CENTRES

Hardness out of the cooling loop at a hyperscale data centre

HydroPURE softening held cooling make-up hardness below 1 ppm, with N+1 redundancy intact at a hyperscale data centre.

SHORTAGE OR SHUTDOWN?
Keep your plant at full rate.